How Long Does a Bathroom Remodel Actually Take?

When a homeowner sits down with me at the Design Center, there's a question that almost always comes up before we've even pulled a tile sample:
"How long does a bathroom remodel take, and how long will we be without it?"
I get it. A kitchen remodel is inconvenient. A bathroom remodel can feel personal, especially if it's the bathroom you use every single morning, or the only full bath in the house.
The good news is that a bathroom is one of the most predictable projects we do. The less-good news is that the part people expect to take the longest (demolition and construction) usually isn't what sets the schedule. Selections, tile, and one item almost nobody thinks about, the shower glass, are what really drive it.
Here's how it actually works.
Quick answer
Most bathroom remodels take about 2 to 4 months from first meeting to finished room. The on-site portion is shorter than most people expect:
Hall or guest bathroom: about 3 to 4 weeks on-site
Primary bathroom: about 4 to 6+ weeks on-site, longer with layout changes, a curbless shower, or heated floors
Tub-to-shower conversion: often 1 to 2 weeks on-site
Custom shower glass: add about 2 to 3 weeks after the tile is finished, because the glass can't be measured until then
The rest of the calendar is design, selections, ordering, and permits, and that's where good planning saves you the most time.
Design & selections
This is my favorite part, and it's also the phase that protects your schedule the most.
After your contract is signed, we'll meet at the Design Center to walk through every finish: floor tile, shower wall tile, accent tile for the niche, the vanity, countertop, plumbing fixtures, lighting, mirrors, and hardware. We'll talk about whether to carry one tile across the floor and walls to make a smaller room feel bigger, and whether your fixtures should match your vanity hardware or play off it.
Plan on 2 to 6 weeks for design and selections, depending on how many decisions there are and how quickly you like to make them. Then ordering begins. Typical lead times:
In-stock tile: about 1 to 2 weeks
Special-order or imported tile: 4 to 8+ weeks
Vanities: 2 to 8 weeks, depending on stock versus custom
Plumbing fixtures: usually 1 to 3 weeks, longer for specialty finishes
My one non-negotiable: every selection is made before demolition starts.
Choosing tile while your bathroom is already gutted is how two-week delays happen. When everything is picked, ordered, and confirmed, the on-site work moves quickly. If you want inspiration before we meet, our posts on 2026 bathroom remodeling trends and walk-in shower ideas for CT homes are a great place to start.
Solimine Contracting Design Center
Permits
If your bathroom remodel involves moving plumbing, adding or relocating electrical (a new exhaust fan, lighting, or a heated floor), or changing walls, your town will require a building permit. A straight swap of fixtures in the same locations sometimes doesn't need one, but most full remodels do.
We handle the application and schedule every inspection for you. In most of the towns we serve, plan on roughly 2 to 4 weeks for a bathroom permit, and timing varies between Connecticut and New York towns. Because we submit while materials are on order, the permit almost never adds time to the overall project.
On-site phases
Here's what a typical hall bathroom looks like once we're on site. A primary bathroom follows the same steps; each phase just has more square footage.
Timing | Phase | What's Happening |
|---|---|---|
Days 1-2 | Protection and demolition | Floors and hallways protected, dust barriers up, old fixtures and tile removed |
Days 3-7 | Rough-ins and framing | Plumbing and electrical moved or updated; shower niche and bench framed; rough inspection |
Week 2 | Waterproofing | Backer board, a fully waterproofed shower, and a properly pitched shower pan, tested before tile |
Weeks 2-3 | Tile | Floor and shower tile set, grouted, and sealed |
Weeks 3-4 | Finishes | Finishes Vanity, countertop, toilet, plumbing trim, lighting, mirrors, paint, final inspection |
After tile | Glass | Shower glass measured, fabricated, and installed |
A few things I always explain to clients:
Waterproofing is the part you'll never see, and the part that matters most. We take our time here. A shower that looks beautiful but isn't waterproofed correctly will cause problems for years.
Tile is the longest phase, and that's a good thing. A large-format porcelain floor goes
quickly. A herringbone pattern, a mosaic floor, or a niche wrapped in accent tile takes longer, because every cut is visible. If the pattern you love adds a few days, it's usually worth it.
Your bathroom is usable before the glass arrives. Once the tile and grout have cured, most clients use their new shower with a simple tension-rod curtain until the glass is installed.
Custom glass lead times
This is the timeline question that surprises almost everyone, so it gets its own section.
Custom frameless shower glass is built to the exact dimensions of your finished shower, down to the fraction of an inch. That means it can't be measured until the tile is completely finished. Walls that look perfectly square almost never are, and the glass has to fit what's actually there.
Once the tile is done, here's the sequence:
• Measure: our glass partner comes out to template the opening
• Fabrication: about 2 to 3 weeks for most frameless and semi-frameless panels
• Installation: usually a few hours, with a short wait before the silicone fully cures
A few choices can stretch that window: specialty hardware finishes (brushed gold or bronze, for example), low-iron "ultra-clear" glass, tinted or fluted glass, protective coatings, and unusual shapes, such as glass that follows a sloped ceiling. None of these are reasons to skip what you love. We just plan around them by finalizing your glass style during design, so there are no surprises at the end.
If you're debating whether you need a door at all, a fixed glass panel for a walk-in shower is often the simplest and fastest option. We cover more of that in Bathtub to Shower Conversion: Do You Really Need that Tub?
Frequently Asked Questions
Can I stay in my home during a bathroom remodel?
Yes. Most of our clients stay home. If it's your only full bathroom, let us know early so we can plan the schedule around it and keep the time without a working shower as short as possible.
How long does a tub-to-shower conversion take?
Usually 1 to 2 weeks on-site, plus 2 to 3 weeks for custom glass after the tile is finished.
Why does tile take so long?
Tile is set in stages: the shower pan and waterproofing first, then walls, floors, grout, and sealing, each with drying time. Intricate patterns and small mosaics also take longer to set than large-format tile.
When is shower glass ordered?
The style is chosen during design, but the glass is measured and ordered only after the tile is complete, so it fits your shower exactly.
How much does a bathroom remodel cost?
Every quote depends on the home, but most hall and guest bathrooms we do fall between $15,000 and $25,000, and most primary bathrooms fall between $40,000 and $60,000. Financing is available for qualified clients; see our financing options.
Let's Plan Your Bathroom
A bathroom remodel done right is one of the most rewarding projects in a home. It's the room that starts and ends your day. When the design is finished, the materials are on hand, and the glass is planned from the beginning, the process feels calm instead of chaotic.